Construction Progress

june 30, 2026

  • Curb and gutters are in place
  • Transformer and meter installation underway
  • Interior office framing in progress

june 3, 2026

  • Mezzanine level installed
  • Electrical room has been constructed
  • Man doors are on the building

MAY 27, 2026

  • 4000-Amp switchgear has been installed
  • Electrical room has been constructed

MAY 11, 2026

  • Roof is on

april 6, 2026

  • Wall panels tilted
  • Wall Raising Event attended by Westminster Mayor Chi Charlie Nguyen, council members, city staff, and representatives of lender, investors, and project team.

March 2, 2026

  • Slab poured/walls being formed

FEBruary 10, 2026

  • Building Pad certified
  • Column footings have been dug
  • Footings poured

January 19, 2026

  • Grading underway

December 20, 2025

  • Construction started on Nov 6, 2025
  • September 2026 completion
  • All existing buildings and foundations have been demolished
  • Currently installing underground sewer and water